Infrastructure & Transport • North Queensland • 5 months

Northern Revetment Wall Rehabilitation

QA/QC, HSE, and environmental compliance systems for the rehabilitation of a 322-metre revetment wall within an active bulk port facility, achieving zero non-conformances at first audit.

Revetment wall rehabilitation project

5 months

Duration

Zero

Non-conformances

Zero

HSE incidents

The Challenge

  • Operational environment: Works conducted within an active bulk port facility requiring continuous coordination with marine operations, vessel scheduling, and tidal conditions.
  • Environmental sensitivity: Construction within a live marine ecosystem demanded strict turbidity controls, fauna spotter coverage, and environmental reporting.
  • Material compliance: Multiple armour rock size classes (50-150 kg, 350-800 kg, 1-2 t) required rigorous source verification, gradation testing, and installation sequencing to meet design tolerances.
  • Access and staging: Tidal windows and fluctuating weather conditions limited working hours, requiring detailed staging and progressive sign-offs.
  • Documentation burden: The project required full traceability from rock source to placement, with ITPs, lot records, and material test results forming part of close-out deliverables.

MESCo’s Role

MESCo was engaged by the principal contractor to establish and manage the QA/QC, HSE, and environmental compliance systems for the rehabilitation of the 322-metre northern revetment wall. MESCo developed and implemented project-specific management plans, QA frameworks, and document control systems to ensure alignment with ISO 9001, 14001, and 45001 standards. MESCo’s structured approach ensured that all armour rock, interlocking, and filter layers were installed in compliance with design and environmental requirements, while maintaining full operational interface with port authorities.

Key Deliverables

  • Project Management and Environmental Plans tailored for marine construction.
  • Full QA/QC framework including ITPs for geotextile, filter, interlocking, and armour rock placement.
  • Lot Register and material traceability register (linked to source quarries and test results).
  • Construction Staging Plan integrating tidal windows and operational coordination.
  • Hold and Witness Point Matrix for all critical activities.
  • Environmental monitoring system including turbidity testing and fauna observation logs.
  • Non-conformance tracking and closure register.
  • Daily QA and environmental status reporting to the principal contractor.
  • As-built and close-out documentation package with survey validation and photographic evidence.

Outcome

  • All QA/QC and environmental documentation accepted at first audit with zero non-conformances.
  • Turbidity limits maintained within regulatory thresholds for the entire duration of works.
  • Full traceability achieved for all armour and filter materials through MESCo’s material tracking framework.
  • Project delivered with no HSE incidents and no disruption to port operations.
  • Client commended MESCo’s documentation control and real-time QA reporting approach.

Lessons Learned

  • Early QA involvement during design validation allowed construction sequencing to align with tidal limitations and inspection requirements.
  • Integrating environmental monitoring within daily QA workflows reduced duplication and ensured continuous compliance visibility.
  • Material tracking from source to placement proved essential for defending compliance during audits.
  • MESCo’s structured documentation and real-time register management improved efficiency and strengthened client confidence in marine project execution.

Other case studies

See all case studies

Mining & Resources

BHT LME04 Diversion Road Construction

Integrated engineering and HSE support for construction of a temporary MAR bypass at Hope Downs 1, delivering a clean close-out package with all tests passed on first submission.

View project

Hope Downs 1 – Bedded Hilltop (BHT), WA

Infrastructure & Transport

Paraburdoo Airport Asphalt Overlay

On-site QA/QC engineering support for a high-stakes asphalt overlay project at an operational airport, delivering zero audit findings and first-submission handover acceptance.

View project

Paraburdoo, WA (Pilbara)